If you are upset about choosing beer brewery equipment of that size, I feel like the following should give you some help.
Here I made some comparisons and analysis between 500L brewery system and 1000L brewery system.
As can be seen from the above table, the 1000 liter beer equipment is 15,000 euros more expensive than the 500 liter beer equipment,
500L Brewery Equipment | 1000L Brewery Equipment | Remarks | |
Configuration |
Almost same, but most of sizes and dimensions are definitely different. | Almost same, but most of sizes and dimensions are definitely different. | All sizes and dimensions could be checked in the quotes. |
Beer Production/Mon |
2000L~4000L depending on how long per brewing cycle | 4000L~8000L depending on how long per brewing cycle | |
Expansion Production/Mon | 10000L~20000L depending on how long per brewing cycle | 20000L~40000L depending on how long per brewing cycle | This is calculated by adding 8 pcs double batches fermenters. |
Floor space | Around 45 ㎡ | Around 65 ㎡ | |
Installation time |
Approximately 20days |
Approximately 20days |
Brewhouse pipes, glycol pipes, cable connecting and debugging. |
Brewing time/batch | Approximately 8 hours | Approximately 8 hours | |
The height of ceiling | It can be customized according the actual height. | It can be customized according the actual height. | |
Power supply |
8.65KW |
12kw |
If the steam boiler uses LPG or natural gas. |
So please feel free to check what beer production is more suitable for you.
If you hope that we can make some comparisons of other sizes’ beer brewing system.please directly email us.