Welcome to view our website, this is Sharon here with project manager from Tiantai Brewery Company.
Here we’d love to share with you this 200l brewing system that just arrived to our customers in Brisbane, Australia and ready to be set up. This is a complete set of brewing project including main configurations from malt mill to Reverse Osmosis water treatment system. Let’s take a detailed look at this system together and if you are looking for similar size of set up for your brewing project, feel free to reach out to us for more interested information please, Cheers!
From the very beginning of received inquiry from our customer to the equipment arrived in the spot, it took about 90 days around for the brewery designing, equipment manufacturing as well as shipment. Here are mainly these time stages:
1) Brewery Layout Confirming and Equipment Drawings Preparation:
Once the order is made, our engineers will start to confirm the brewery layout and design the technical drawings for the tanks immediately, and then our factory will start manufacturing based on the drawings exactly. This will take about 7-14 days;
2) Fabricating Time: when the drawings are ready, materials gathering and fittings purchasing work is getting started, and then the complete production would begin from tanks body to jacket, inner tanks to the pipeline connection finally. During this time, we will run a complete testings and inspections from inner layer to the whole tanks. And then handle details, clarify accessories, post processing and final finishing is proceeded. This will take about 70-80 days to make sure the tanks quality.
3) Shipment Arrangement: when the production is almost completed, we will start to book vessels and prepare the related customs documents, the shipment time depends based on different countries.
For this size of brewing system, usually a 20 foot container would be enough to load all cargoes. Main configurations included in this system:
1) Malt Mill;
2) 200L 2 Vessel Brewhouse[Mash/Lauter Tun+Kettle/Whirlpool Tun+Hot Liquor Tank] with Gas Fire Heating;
3) 200L Fermentation Tanks;
4) 2 Station Manual Keg Washer;
5) 500L/Hr Reverse Osmosis Water Treatment Machine.
6) Control Cabinet.
Heating source is one of the essential factor that needs to be considered when choosing a brewhouse, whether electric, steam or direct fire are all good options for the brewery depends on a rage of factories, including brewhouse size, available utilities, and the initial&ongoing costs, etc. are all needs to be considered when making a decision.
Direct Fire Heating
As a relatively more traditional heating source, gas fire heating are still popularly used in some regions that has expensive cost of electric consuming or finding a steam generator. Our gas fire set up composed by closed combustion chamber to ensure the safe operations and room temperature control, etc.
Turnkey solutions, customization services and all possible technical support are all available to be provided to meet your requirements, just feel free to reach out to us with your demands and we’d be more than happy to work together with you finding a suitable solution to help you project running.
Thanks a lot for your time and attention and we wish all the best with your business!